EDrill-2 departed COSCO Shipyard on 29th November after pre-mobilization inspections and third party equipment installation to arrive at the Gulf of Mottama location on 21st December. The rig has safely and successfully completed it’s mooring system field tests and heavy lifting operations with the DES set up on the first Zawtika wellhead platform. The first well’s top hole section has been drilled, cased and cemented.
EDrill-2’s light-weight Drilling Equipment Set (DES) erects in four lifts and is handled by a large radius, 400MT crane which allows the tender barge to orient favorably in prevailing sea states and to minimize vessel motions for quick and safe rig moves. Zawtika Development Drilling Campaign (Phase 1B + Infield Phase 1A + Phase 1C) consists of around sixty-seven wells to be drilled from ten wellhead platforms in water depths of up to 160m.